The Latoria Creek Park stairs will cost an estimated $325,000 to replace when engineering design, materials and construction are factored in. (Photo courtesy of City of Colwood)

Colwood says $325k price tag for stairs covers more than just building costs

Price estimate encompasses design, materials and construction

The $325,000 price tag for new stairs at Latoria Creek Park encompasses more than just the cost of building the stairs, according to the City of Colwood.

Last week, some readers expressed through Facebook comments that the cost of the stairs is “obscene.”

But on Friday, the City put out a news release stating that the estimated $325,000 cost covers detailed engineering design, materials and construction.

The amount is one of three estimates used in a Canada Infrastructure grant application that the city applied for to help pay for the cost of replacing the stairs.

READ MORE: Colwood applies for $325k to replace stairs in Latoria Creek Park

“This amount is the highest of the three estimates, and comes with the longest life span, lowest maintenance cost, and lowest overall cost for the City and taxpayers over time,” the release said.

There are a total of four steep staircases in Latoria Creek Park, each with up to 112 steps. The work to replace them would be done over three years.

The first set of stairs is almost one kilometre along a forest trail with the creek below on one side and steep, rocky slopes on the other.

The City said the location of the stairs presents challenges when it comes to replacement because materials cannot be trucked or craned in since the stairs are deep in the park.

“They would need to be fabricated off site and transported in sections,” the release said.

READ MORE: Readers fin $325,000 price tag for Colwood stairs to be “obscene”

Proposed materials for the stairs would be an aluminum structure with wood components to fit the natural forest setting.

The steps are in need of replacing after a 2018 inspection revealed that several steps were rotting and unsafe. Temporary repairs were done but according to an assessment that was done at the time, replacement is still necessary to ensure the stairs continue to be safe and usable over the long-term.

The City received 200 signatures in support of applying for the federal grant which will cover 73 per cent of the replacement cost. The remaining 27 per cent — or $87,000 — would be covered by the City. There would be zero tax increase to Colwood residents for this work.

shalu.mehta@goldstreamgazette.com


Like us on Facebook and follow us on Twitter

Just Posted

Malahat snow-covered as flakes fall across Greater Victoria

Snowfall warning in effect for parts of Vancouver Island

BC Housing remains open to modular housing in Saanich, but acknowledges slow regional up take

Only one project with 21 units underway in the Greater Victoria

West Shore lands Pan Am Cross Country Cup

Event coming to Westin Bear Mountain Golf Resort Spa in February 2020

Pacific FC to face off against HFX Wanderers FC at inaugural match

First game at Westhills Stadium on April 28

What’s going on this weekend in Greater Victoria, Feb. 22 to 24

Music, theatre, musical theatre, and home shows

Fashion Fridays: Must have wardrobe basics

Kim XO, helps to keep you looking good on Fashion Fridays on the Black Press Media Network

POLL: Will you be wearing pink to take a stand against bullying?

Schools and workplaces across Greater Victoria and around the province will be… Continue reading

Skier dies at Revelstoke Mountain Resort

Cause of death for young man has not been released

R. Kelly charged with 10 counts of sexual abuse

R&B star has been accused of sexual misconduct involving women and underage girls for years

More sailings coming to 10 BC Ferries’ routes

Transportation Minister Claire Trevena said the sailings were originally cut in 2014

National Energy Board approves Trans Mountain pipeline again

Next step includes cabinet voting on the controversial expansion

Cryptocurrency exchange CEO who suddenly died leaves Kelowna house in will

Gerald Cotten, holding the keys to money tied up in his virtual currency exchange, died in December.

Regulator’s report, coming today, unlikely to settle Trans Mountain pipeline battle

The Trans Mountain pipeline will remain a controversial topic both in the political ring and out

Most Read