Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Woodwynn Farms to be shut down and sold

The rehabilitation program at Woodwynn Farms is being shut down. According to… Continue reading

False missile alert for Central Saanich councillor

While on vacation in Hawaii, Central Saanich Councillor Alicia Holman was awoken… Continue reading

Victoria airport nearing billion-dollar mark in economic impact

Airport has nearly doubled its passengers and its impact on the economy since 2005

More buoys allowed for Brentwood Bay

Proposed number rises from 40 to 60

Victoria airport reaches nearly two million passengers in 2017

This year expected to see additional growth

Sidney’s Salish Sea aquarium to close for maintenance

First extended closure for the Shaw Centre for the Salish Sea since it opened in 2009

Butchart Gardens is hiring now and paying more

Wages start at $15, job fair Feb. 20

Cash still needed for Stelly’s Cross Path

MLA Olsen wants more specifics first

Injured parachutist wants stolen backpack back

Bag contained important video files of 2017 parachuting incident

World’s fastest log car made in B.C. sells for $350,000 US

Cedar Rocket auctioned off three times at Barrett-Jackson Co., netting $350,000 US for veterans

Bad timing: Shutdown spoils Trump’s one-year festivities

Trump spends day trying to hash out a deal with Senate Minority Leader Chuck Schumer

RCMP nail sex toy thief

Shop owner plays a role in arrest

Ice-cream-eating bear draws controversy

An Alberta Wildlife Park posted a video this week of one of their bears going through a Dairy Queen drive-through

LETTER: The sewage spiral continues in Greater Victoria

My left brain has been trying to digest the news and comments… Continue reading

Most Read