The Trans Canada Highway at Salmon Arm is subject to the latest of a long series of widening projects extending to the Alberta border. (B.C. transportation ministry)

The Trans Canada Highway at Salmon Arm is subject to the latest of a long series of widening projects extending to the Alberta border. (B.C. transportation ministry)

B.C. highway widening job reduced, costs still up $61 million

Union-only project scales back work to widen Trans-Canada

The B.C. NDP government’s union-restricted road construction program is sparking new questions about a steep increase in costs, even as a section of Trans-Canada Highway widening work has been significantly scaled back.

Widening the Trans Canada Highway east of Kamloops is one of three major projects the NDP government designated for what it describes as “community benefits agreements.” They restrict the workforce to 19 mostly U.S.-based construction trade unions under a 336-page agreement with a new Crown corporation created to administer it. The others are replacement of the Pattullo Bridge at Surrey, and the Broadway subway extension in Vancouver.

The latest contract to be let under the agreement is for a section of Highway 1 at Salmon Arm, announced in June at a budget of $185 million, including $31 million from Ottawa. The announcement by Transportation Minister Claire Trevena explained the reduced size, three-year delay and $61 million increase in costs was because the 2016 project was completed without sufficient engineering and local engagement work.

Kamloops-South Thompson MLA Todd Stone, the former B.C. Liberal transportation minister, said the work was done by 2017, including consulting the Neskonlith Band. Questioned on the project by Stone and Shuswap MLA Greg Kyllo, Trevena said there is still no agreement with Neskonlith to proceed with a large portion of the widening.

Stone said the 9.9 km project has been reduced to 4.9 km, “with a two-lane section stuck in the middle between Hoffman’s Bluff and Chase West,” and elimination of an underpass.

“These massive cost overruns and project scope reductions are the direct result of the NDP delaying these projects for upwards of three years, on top of additional costs in the millions of dollars resulting from the NDP’s imposition of community benefit agreements requiring projects to utilize labour of one of 19 NDP approved unions,” Stone told Black Press July 6.

Trevena said agreement with Neskonlith is needed for the federal share of the money to be provided, and other costs were affected by a “hot market” for construction, up until the COVID-19 pandemic had broad effects on the economy.

“I think what we have now is the realistic budget,” Trevena said.

A tight construction labour market and high prices for steel and asphalt were also cited in the 35-per cent jump in cost for the first contract awarded under the union agreement, east of Revelstoke.

Trevena noted the first Salmon Arm contract went to a Kamloops-based company, and said the new union structure ensures more local, female and Indigenous people being hired as apprentices. That claim has been a source of bitter dispute with newer unions and non-union construction companies, who say they employ 85 per cent of people currently working in construction trades.

Premier John Horgan and the B.C. and Yukon Building Trades say it’s the completion of apprenticeships that is most important, and traditional building trades have an edge there.

RELATED: Contractors picked for Pattullo Bridge replacement

RELATED: Cost jumps 35% for Revelstoke widening section

The new Crown corporation, B.C. Infrastructure Benefits, controls payroll, union dues and benefits for designated public projects. It diverts an additional 25 cents per hour worked to a new union organization called the Allied Infrastructure and Related Construction Council of B.C., and another seven cents per hour to building trades union funds for health and safety.

Non-union or independent union-affiliated companies can still bid on projects, but their employees are required to join one of the designated international unions within 30 days of starting work.

When the $1.38 billion contract to build a new Pattullo Bridge was awarded in January, Trevena acknowledged that the union-only deal would add about seven per cent to the cost. The 83-year-old four-lane bridge is being replaced with another four-lane bridge with added pedestrian and bicycle lanes, and a new off-ramp to Highway 17, the South Fraser Perimeter Road.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Kennedy Nikel, applied marine biologist at Cascadia Seaweed, here seen in late September, shows off bull kelp (in her left hand) and rock weed. The company is spear-heading an annual seaweed festival scheduled for May 13-21, 2021, with Sidney council have signed off in principle. (Wolf Depner/News Staff)
Cascadia hopes to see Sidney host seaweed festival in May 2021

Council supports the idea in principle following a presentation by Cascadia Seaweed

GIF
’90s rock band resurfaces with songs never properly recorded or released

Underwater Sunshine’s online reunion involves four guys who lost contact for years

Tim Siebert, one half of the partnership behind Citrus & Cane, says opening the Douglas Street cocktail lounge during a pandemic had challenges, but the bar is ready to adapt to whatever comes next. (Nina Grossman/News Staff)
New Victoria tropical cocktail lounge designed with COVID-19 safety in mind

Citrus & Cane opens in site of former Copper Owl after eight-month delay

Trevor Davis, base manager of the Western Canada Marine Response Corporation in Sidney, stands in front of the Hecate Sentinal, an oil skimming vessel based at Sidney’s Van Isle Marina. (Wolf Depner/News Staff)
Oil spill response base taking shape on Saanich Peninsula

Enhanced base with elements in North Saanich and Sidney to be fully operational in fall 2022

Idyllic winter scenes are part of the atmosphere of the holiday season, and are depicted in many seasonal movies. How much do you know about holiday movies? Put your knowledge to the test. (Pixabay.com)
QUIZ: Test your knowledge of holiday movies and television specials

The festive season is a time for relaxing and enjoying some seasonal favourites

Black Press Media and BraveFace have come together to support children facing life-threatening conditions. Net proceeds from these washable, reusable, three-layer masks go to Make-A-Wish Foundation BC & Yukon.
Put on a BraveFace: Help make children’s wishes come true

Black Press Media, BraveFace host mask fundraiser for Make-A-Wish Foundation

A man walks by a COVID-19 test pod at the Vancouver airport in this undated handout photo. A study has launched to investigate the safest and most efficient way to rapidly test for COVID-19 in people taking off from the Vancouver airport. The airport authority says the study that got underway Friday at WestJet’s domestic check-in area is the first of its kind in Canada. THE CANADIAN PRESS/HO, Vancouver Airport Authority *MANDATORY CREDIT*
COVID-19 rapid test study launches at Vancouver airport for departing passengers

Airport authority says that a positive rapid test result does not constitute a medical diagnosis for COVID-19

A small crash in the water south of Courtenay Saturday afternoon. Two men had to be rescued, but reports indicate there were no serious injuries. Photo by Mike Chouinard
Small plane crash in Comox Valley waters Saturday afternoon

Two rescued from plane that had flipped in water; no serious injuries reported

A photo from 2017, of Nuchatlaht First Nation members outside court after filing a land title case in B.C. ( Submitted photo/Nuchatlaht First Nation).
Vancouver Island First Nation calls on B.C. to honour UNDRIP in historic title case

Nuchatlaht First Nation says Crown counsel continues to stall the case using the ‘distasteful’ argument that the Nation ‘abandoned’ their land

West Vancouver Island’s Ehattesaht First Nation continues lock down after 9 active cases were reported today after a visitor tested positive last week. (Ehattesaht First Nation/Facebook)
Ehattesaht First Nation’s COVID-19 nightmare: nine active cases, a storm and a power outage

The Vancouver Island First Nation in a lockdown since the first case was reported last week

114 Canadians were appointed Nov. 27 to the Order of Canada. (Governor General of Canada photo)
Indigenous actor, author, elder, leaders appointed to Order of Canada

Outstanding achievement, community dedication and service recognized

The Ahousaht First Nation confirmed its first case of COVID-19 on Nov. 26, 2020. (Westerly file photo)
Ahousaht First Nation on lockdown over COVID-19

“Emotions are high. The anxiety is high. We want our community to pull through.”

Most Read